Retro Fitting of Dry Verge If dry verge units are to be fitted to existing buildings all of the old undercloak and mortar bedding should be removed prior to fixing. Marley ventilated dry ridge system is designed to provide a totally dry fixed and weathertight ridge that is not only the best available system on the market, but is also fast and simple to install. Every ridge unit is mechanically fixed eliminating the need for mortar completely.


The system is suitable for use with all Marley tiles and slates. Dry ridge conversion – This is an old concrete interlocking tiled roof approximately years ol the mortar was removed and converted to a dry ridge system.

This was done for ventilation improvements and lack of future maintenance. Universal RidgeFast is a low cost, ventilated dry ridge system suitable for use with all standard ridges, tiles and slates. Please note: not suitable for degree.


This video shows the basics of installing a dry ridge system to a hip ridge , instead of a straight top run as in the previous videos. This method can also be used to fit a dry hip ridge to slate. Ridge and Hip Fixing Kits Datasheet pdf. Our easy to follow step by step instructions allow homeowners to take control of the project with confidence.


This part specifically deals with two common types of roof construction and how to fit the brackets for the ridge batten.

Installing Dry Verge to Existing Buildings Once all under cloak and mortar has been removed a timber batten can be installed running from the eave to the ridge. Lay the underlay and batten the roof in the normal manner, but do not fix the top tiling batten at this stage. Ensure that the top batten is as close to the ridge. Continuous Dry Verge System Fitting Instructions Continuous dry verge system is designed to fit on the gable end of buildings between the underside of the battens and the outer wall of the roof ladder.


The link at the top of the page is my page on dry ridge where I link to my current favorite dry ridge kit, alternatives and information. Dry hip ridge conversion – This video shows a dry ridge install to a hipped roof, which is slightly different from a simple top run of ridges. Extend the tiling battens 20mm beyond the gable wall or barge board and nail a Batten End Clip to the end of every batten. If a batten end clip is not being used we recommend that the. The kit is supplied with fitting instruction to help you through the process but be assure fitting is quick and easy compared to mortar fitting and other dry -fix systems.


Continuous Dry Verge should be cut to the required length allowing for a plumb cut at the ridge , and approximately 150mm longer than the rafter. The horizontal flange is cut away, to allowing fitting over the felt support tray at the eaves. The design of the system allows the units to be used o. Fitting instructions can be found on the Manthorpe Website. HDRVF_ValleyTrough_leaflet_bk_5c Valley Intersections Where a section of Dry Valley intersects with another section of Dry Valley e. My fascias and pointing need doing on the house I have brought but as costs are mounting I thought I would install some dry verge caps to get me through winter and do. We use cookies to ensure that we give you the best experience on our website.


Our costs for supplying and fitting dry verge to gables plus a couple of dormers is roughly £ 950.

I,d need to take a look first and be within mile radius of DE15. Place the next verge tile in to position and fix in the usual manner. Natural Slate Continuous Dry Verge Fixing Instructions 1. The top of the gable wall should be reasonably level and free from obstructions. PVC dry verge (end of the roof) is specially designed to block any gaps that could permit birds or large insects entering the roof space. Free delivery and returns on all eligible orders.


A classically designed turntable and category first for House of Marley. The STIR IT UP turntable is simple in form and rich in materials with natural bamboo details. Additional components may be required for hips). Making installation even easier, the ambidextrous dry verge systems are easily adapted on site to fit either the left or right hand verges of the roof, meaning only one verge unit is required rather than two.


Unlike conventional dry verge systems each verge unit is designed to be nailed onto the top of the tile battens, thus eliminating the problems sometimes associated with nailing into the end grain of tile battens. These new systems have been designed over the past few years by three main companies who are Klober Man. All the components are of high quality and manufactured to make installation quick and simple. This dry ridge system includes a ventilated ridge roll with self-adhesive butyl strip, stainless steel fixing pack, ratchet unions the super strength nylon ratchet clips.


Files are supplied in Adobe Acrobat (PDF) format. Multiverge - Dry verge systems The Sandtoft multiverge system has been specifically designed to suit most single lap large format concrete and clay roof tiles. The Dry verge units are handed to suit both sides of the verge as are the stop end units which are fixed in the eaves dry verge units.


Our parent company NWA pioneered and invented the slate dry verge system whIch has helped protect thousands of roofs across Ireland and the UK from the elements, especially high wind damage which causes slates. Product DescriptionMarley Eternit Universal Dry Verge provides a strong, weather tight and mortar free verge solution for the majority of tiles within all three main. The whole unit is then fixed into place with a screw and a. The effect of recent cold winters cannot be overstated and is why one area of the revised Chapter, discussed on page specifically addresses mortar placement to verges, which NHBC has seen to be susceptible to the effects of.


Tileline Combination dry fix ridge system.